Week 8:
Friday, July 31, 2009
Thursday, July 23, 2009
Friday, July 17, 2009
Week 6:
Next week we will begin painting the house. Stay tuned for more updates!! :o)
Friday, July 10, 2009
Friday, July 3, 2009
Week 4:
This week at Pitt St. we had the insulation company insulate the whole house.


The electrician finished his electrical rough-in of the house. We put 5 can lights in the kitchen and a pendant light for over the island. The electric company will be putting in the electric meter on Tuesday.
This week the plumber was able to finish his rough-in plumbing also, along with the HVAC company.
Next week we will be starting the Drywall process. Things will begin to pick-up at this stage and the house will be completed in no time at all!! :o)